No work on the project today but yesterday Mike and I decided to use expanding foam
insulation around the perimeter of the hangar walls where they meet the concrete
floor. Earlier in the year the floor had a bunch of water on it which was
caused by snow piled up at the far end of the hangar row. As the snow melted,
the runoff made its way from hangar to hangar including the DOG Aviation
hangar. In an effort to make a preemptive strike at eliminating water in the
hangar, decided to try sealing the base of the metal hangar walls with
expanding foam which will hopefully act as a dam and prevent water from
entering from adjacent hangars. So everything that was placed along the walls
was pulled out so the floor could be swept and blown with air from Mike’s portable
air compressor.
Mike applying the expanding foam to the base of the back wall of the hangar. The treated area can be seen on the left.
Mike laying out a nice bead of expanding foam
along the back wall of the hangar.
After the expanding foam was applied, the shop
was straightened out once again and I decided to use the big air compressor for
the first time. Plugged it in, turned it on … and it barely began to turn.
What? Decided to try another outlet that I know is on another circuit and the air
compressor turned a little faster … but still no dice. Bummer. Scotty, I need more power!
Got to thinking about it and it is a 13 amp
compressor so it takes more than a little power to get it moving. The circuit is only 12
gauge wire and the wire run goes to the breaker panel at the far end of the
hangar row which wire distance is likely around an easy 200 feet. The 12 gauge wire has
much more voltage loss than optimum … but one thing is certain … the air compressor
will NOT be running on house power.
Guess it is time to go shopping for a small
portable generator …that sucks but shy of running a #6 wire, just don’t think
there is anything that can be done.
Even though my exuberance was squashed due to
the anemic electrical outlets in the hangar, decided to suck it up and make
something happen on the RV-12 … so moved the tail cone in close proximity behind
the fuselage so the wiring to and from the tail cone could be installed, along
with pulling the pitot tube through the fuselage’s center section. My method
for doing this is a departure from the Van’s plans which would have the builder
doing this with the side skins on … but there is a method to the madness, so to
speak. The plan is to install a backup altimeter and airspeed indicator in the
RV-12’s instrument panel which will require running a static air tube up to the
instrument panel plus there is the angle of attack indicator tubing which needs
to be run back to the tail cone. The wire grommets are getting really full and
I know there is room for the trim wires and pitot tube … but just in case the
static air or AOA tubing won’t fit, by having the side skins off, it will offer
options for routing in case the wire grommets get maxed out.

Routing the pitot tube in through the center
tunnel wire grommets.
After the pitot tube was routed, up through the
center tunnel, the wire that goes to the pitch trim motor was pulled in through
the wire grommets in the center tunnel.
Routing the pitch trim motor wire through the
center channel wire grommets.
Finished for now the pitot tube and pitch trim
motor wire successfully run through the center tunnel wire grommets.
A test piece of the static line was able to fit
into the aft grommet on the fuselage which is great news … however, the center channel
grommet has one more 18 gauge wire in it so it may not be a piece of cake
getting it pulled in through the center tunnel. Hopefully, will give it a go tomorrow if other
obligations get fulfilled in the morning.